2016-11-02 - 28002 - Rel Notes - Fix counter on rescheduling #SAPReleases2016

Release Notes - Draft


28002 : Fix counter on rescheduling


Admin Info



Purpose
Fix counter on rescheduling
Release No
001
Submitted on
11/2/2016
Submitted by
Surya Basa
Environment
NECNED to NECNEQ
Sent To
Dan Brennan
Object(s) created by
Damodhier Sanagana
Object(s) tested by
Surya Basa
Transport Status
Created in NECNED100

Transport and Technical Objects


Sl.
Transport ID
Description
Object Name
1
NEDK937789
SD:28002:ReschedulingChanges to fill Cus.table for PO Qty/Dd
ZCL_IM_ME_PURCHDOC_POSTED
ZME_PURCHDOC_POSTED
ZSD_RESCH
2
NEDK937815
SD:28002:Resch.wrapper program&Post proc.chgs for Cus. Table
ZRSD_RESCHEDULING_DEL
ZSD_WRAPPER_RESCH





Release Notes


For Infrastructure


The transports should be imported in the above sequence

For Requestor


NA


Test Notes


System : NECNED500

Test ID
Scenario
Expected Results
Actual Results
Documents
P/F
Notes
Tested By
QA By
SD001
Integrity Test - Compare standard with Z prg
- 0116 variant in simulation mode with Std prg
- 0116 variant in normal mode with Z prg
Results of the both the jobs should be consistent
Ztable - 16 mat
After Job - 12 mat (matched spool data)
10029527
10047537
11032785
10982652
10047285
10047653
11089836
11089837
11089838
11089835
11089839
70217116
10003436
10002059
10234047
10234048
P
N/A
Surya Basa
Deepak Yasam
SD002
Create job with 5 variants - 0116/7/0210/80/0510 (5 steps) ; each variant 20K materials
Step - 6 should be the post processing/clean up program
- Child jobs should be triggered for each variant
- Rescheduling should be performed on the sales orders and spool/log updated updated correctly
- Clean up program should update the Ztable by deleting materials that do not satisfy the criteria
Child jobs triggered for all the variants and spool
was updated; ztable was updated and unwanted
materials were removed
NA
P
N/A
Surya Basa
Deepak Yasam
SD003
Run the above job - variant 0117 to be blank
Child job should not be triggered for 0117 and the remaining
variants/steps should be processed
Child job didn't trigger for 0117
NA
P
N/A
Surya Basa
Deepak Yasam
SD004
Run the job in test 1 with variants 0117/0510 blank
Child jobs should not be triggered for 0117/0510; other variants/steps
should be processed
Child jobs didn't trigger for 0117 and 0510
NA
P
N/A
Surya Basa
Deepak Yasam
SD005
User Exit - Update qty/delivery date on a given PO
Ztable should be updated with the corresponding materials
Materials were updated to the ztable
000000000070064101 - Qty Change
0210 Plant
000000000010743382 - Dt change; 0510 plant
P
N/A
Surya Basa
Deepak Yasam
SD006
Open SO - Open SO on 0116 and not on 0117 (different materials)
Rescheduling should not be carried for the material on 0117 but should on 0116;
post processing prg should remove the materials from the ztable
Rescheduling was carried out for the SO on 0116 but
not on 0117; post processing program deleted the materials from the ztable
70187777 - 0116
11045058 - 0117
P
N/A
Surya Basa
Deepak Yasam
SD007
Open SO - Open SO on 0210 and not on 0510 for the same material; SO delivery
date outside RLT
Rescheduling should not be carried for the material on 0510 and 0210;
post processing prg should remove the material from 0510 and not on 0210
Rescheduling was not carried out for for the material
on 0210 and 0510; material remained on 0210 and removed from 0510
10743382 - 0210 and 0510
SO - 1959758
P
N/A
Surya Basa
Deepak Yasam
SD008
Credit Block - Open SO on credit block on 0210 and not on 0510 for the same
material
Rescheduling should not be carried for the material on 0210 but should on 0510;
post processing prg should not remove the material from 0510 and 0210
Rescheduling was carried out for for the material
on 0210 but not on 0510
1959761 - 0210
4500105138 - 80037547 - 0510
P
N/A
Surya Basa
Deepak Yasam

Rescheduling_Wrapper Prg.xlsx

System: NECNEQ100



Test ID
Test Scenario
Expected Results
Actual Results
P/F
Documents
Notes
Tested By
QA By











Reference Document (Specification or Production Support Break Fix)



SD - Surya - Damodhier - 2016-09-12 - 28002 - Spec - Fix counter on rescheduling (Dan by 2016-09-23)